HMGICS Driving Accuracy and Stability Test Plan
Basis: 2 different nodes, 5 repetitions per identical node | Narrow-space testing
Test cases
19
across 4 categories
Runs planned
89
from the plan sheet's repetitions
Runs prepared
113
over 15 test ids
Scheduled
7 Sept 2026
through 14 Sept 2026
Test plan
What is to be run, on which node, under which conditions, and what it has to hit to pass. Grouped by test item; anything a group shares is stated once above its table.
Stopping Accuracy
Straight-Node Stopping Accuracy
Stop at the designated node after a straight approach
- Objective
- Verify straight-node stopping accuracy and repeatability across different nodes
- Measures
- X error (mm), Y error (mm), heading error (deg), 3σ, success rate (%)
| Date | Node | Reps | Planned | Acceptance criteria |
|---|---|---|---|---|
| Node 1 | 5 | 5 |
| |
| Node 2 | 5 | 5 |
|
Curve-Node Stopping Accuracy
Enter curve → traverse curve → stop at designated node
- Objective
- Verify stopping accuracy across different curve radii and nodes
- Measures
- Stop-position error, heading error, overshoot occurrence, repeatability
| Date | Node | Radius (m) | Reps | Planned | Acceptance criteria |
|---|---|---|---|---|---|
| Node 3 | 1.0 | 5 | 5 |
| |
| Node 4 | 1.0 | 5 | 5 |
| |
| Node 5 | 1.5 | 5 | 5 |
| |
| Node 6 | 1.5 | 5 | 5 |
| |
| Node 7 | 2.0 | 5 | 5 |
| |
| Node 8 | 2.0 | 5 | 5 |
|
Docking Accuracy
Docking Accuracy
Dock after a curved approach
- Objective
- Verify curve-approach docking success and accuracy across different nodes
- Measures
- X error (mm), Y error (mm), heading error (deg), 3σ, success rate (%)
| Date | Node | Yaw (°) | Reps | Planned | Acceptance criteria |
|---|---|---|---|---|---|
| Node 9 | 80 | 5 | 5 |
| |
| Node 10 | 80 | 5 | 5 |
| |
| Node 9 | 90 | 5 | 5 |
| |
| Node 10 | 90 | 5 | 5 |
| |
| Node 9 | 100 | 5 | 5 |
| |
| Node 10 | 100 | 5 | 5 |
|
Initial-Pose Convergence
Initial-Position Offset
Verify drivability after pure rotation
- Objective
- Verify MPPI convergence and drivability when the initial pose differs from the planner heading
- Measures
- Stop-and-Go Rotation Count; Continuous Rotation Status; Rotation Start Delay (s); Path Deviation (mm); Goal Reached
| Date | Node | Yaw (°) | Reps | Planned | Acceptance criteria |
|---|---|---|---|---|---|
| Node 11 | 45 | 3 | 3 |
| |
| Node 11 | 60 | 3 | 3 |
| |
| Node 11 | 75 | 3 | 3 |
|
Narrow Space
Travel Driving
Pass through narrow section with pallet assumption (Payload: 1 ton)
- Objective
- Verify safety and success rate for travel through a narrow space
- Measures
- Collision occurrence, driving success
| Date | Node | Lateral clearance | Reps | Planned | Acceptance criteria |
|---|---|---|---|---|---|
| Node 12 | EVO worst-case condition: 1.95 m | 5 | 5 |
|
Docking Driving
Dock in narrow section with pallet assumption (Payload: 1 ton)
- Objective
- Verify safety and success rate for docking in a narrow space
- Measures
- Collision occurrence, driving success
| Date | Node | Lateral clearance | Reps | Planned | Acceptance criteria |
|---|---|---|---|---|---|
| Node 13 | EVO worst-case condition: 1.95 m | 5 | 5 |
|
Result entry
The blank log the results go into, one line per test id. Nothing has been recorded yet, so this is the checklist itself rather than a report.
Blue text indicates on-site input fields. Position error is calculated automatically when X/Y errors are entered.
Recorded per run
- X Error (mm)
- Y Error (mm)
- Position Error (mm)
- Heading Error (deg)
- Overshoot/Collision
- Minimum Wall Distance (m)
- Pass/Fail
- Video/Log Link
- Remarks
Stopping Accuracy
| Test ID | Test item | Node | Radius (m) | Runs |
|---|---|---|---|---|
| SA-ST-N1 | Straight-Node Stopping AccuracyStop at the designated node after a straight approach | Node 1 | — | 10 |
| SA-ST-N2 | Straight-Node Stopping AccuracyStop at the designated node after a straight approach | Node 2 | — | 10 |
| SA-CV-R1p0-N1 | Curve-Node Stopping AccuracyEnter curve → traverse curve → stop at designated node | Node 1 | 1.0 | 10 |
| SA-CV-R1p0-N2 | Curve-Node Stopping AccuracyEnter curve → traverse curve → stop at designated node | Node 2 | 1.0 | 10 |
| SA-CV-R1p5-N1 | Curve-Node Stopping AccuracyEnter curve → traverse curve → stop at designated node | Node 1 | 1.5 | 10 |
| SA-CV-R1p5-N2 | Curve-Node Stopping AccuracyEnter curve → traverse curve → stop at designated node | Node 2 | 1.5 | 10 |
| SA-CV-R2p0-N1 | Curve-Node Stopping AccuracyEnter curve → traverse curve → stop at designated node | Node 1 | 2.0 | 10 |
| SA-CV-R2p0-N2 | Curve-Node Stopping AccuracyEnter curve → traverse curve → stop at designated node | Node 2 | 2.0 | 10 |
Docking Accuracy
| Test ID | Test item | Node | Runs |
|---|---|---|---|
| DA-N1 | Docking AccuracyDock after a curved approach | Node 1 | 10 |
| DA-N2 | Docking AccuracyDock after a curved approach | Node 2 | 10 |
Narrow Space
| Test ID | Test item | Node | Lateral clearance | Runs |
|---|---|---|---|---|
| NS-MOVE | Travel DrivingPass through narrow section | Applicable Section | Input required | 5 |
| NS-DOCK | Docking DrivingDock in narrow section | Applicable Docking Node | Input required | 5 |
Initial-Pose Convergence
| Test ID | Test item | Node | Yaw (°) | Runs | Remarks |
|---|---|---|---|---|---|
| OF-Y45 | Initial-Position OffsetVerify drivability after pure rotation | Test Node | 45 | 1 | Repetition count not specified; template row |
| OF-Y60 | Initial-Position OffsetVerify drivability after pure rotation | Test Node | 60 | 1 | Repetition count not specified; template row |
| OF-Y90 | Initial-Position OffsetVerify drivability after pure rotation | Test Node | 90 | 1 | Repetition count not specified; template row |
15 test ids, 113 runs prepared for entry. No result has been recorded yet.
Result summary
The workbook's tally, with the two counts it can be checked against beside it.
| Category | Plan sheet | Entry log | Summary sheet | Completed | Pass | Fail | Pass rate |
|---|---|---|---|---|---|---|---|
| Stopping Accuracy | 40 | 80 | 80 | 0 | 0 | 0 | — |
| Docking Accuracy | 30 | 20 | 20 | 0 | 0 | 0 | — |
| Narrow Space | 10 | 10 | 10 | 0 | 0 | 0 | — |
| Initial-Pose Convergence | 9 | 3 | 3 | 0 | 0 | 0 | — |
| Total | 89 | 113 | 113 | 0 | 0 | 0 | — |
Plan sheet is the repetitions the test plan asks for; Entry log is the blank rows the result sheet lays out; Summary sheet is the workbook's own planned figure, transcribed as it stands.
The three sources do not agree for Stopping Accuracy, Docking Accuracy, Initial-Pose Convergence. All three are shown as transcribed rather than reconciled — which one is current is the test team's to say.
Note: The number of repetitions for the initial-pose convergence test was not specified. One template row is provided for each Yaw condition. Copy the corresponding row in the Test Result Input sheet if additional repetitions are required.